T-2 with Officers' Row in the background 2003
[Heritage Hall] | Projects Intro | Carriage Houses | T-1 Proposal | Discussion | Exterior Restorations | Tile Roof Repairs |

Heritage Hall — T-2 Renovation Project at NRHC

Front of T-2 aka Heritage Hall

Three remodeling phases will transform historic T-2's gymnasium into "Heritage Hall," a multi-purpose community/event center with a capacity of about 200 persons. Restoration architect Jim McDonald oversees the project's historic preservation.

Phase I Remodeling Plan

The first phase renovations, scheduled for completion late fall 2004, will meet building codes so that the hall can accommodate about 200 persons. [See Missoulian June 2004 article.]

The major renovations include:

New code-conforming exit doors will open from the Hall onto the six acres of tree-encircled lawns known as the Parade Grounds.